Slab prep work at the 1st floor slab on grade.


Floor box rough-ins at the 1st floor slab on grade.


Floor box rough-ins at the 1st floor slab on grade.


Slab prep work at the 1st floor slab on grade.


View overlooking the 1st floor slab on grade.


Installation of the Chiller slab area footings and retaining walls.


View overlooking the 1st floor mechanical room.


East retaining wall of the loading dock area.


Retaining wall at the west side of the loading dock.


Masonry wall at the 2nd floor of the Student Union.


Floor box rough-in at the 2nd floor.


Conduit installation at the 1st floor slab on grade.


Return to Construction Updates Index Page.




ValpoAdditions and corrections for this page may be directed to Web.Coordinator@valpo.edu
Copyright © 1995 - 2003 Valparaiso University. All Rights Reserved.
This page was last updated 4/14/03 11:24:29 AM CT