Brick installation at the southwest stairtower.

Brick installation at the west elevation.

Brick installation at the interior of the southwest stairtower.

Precast installation at the west elevation.

In wall rough-ins at the 1st floor.

Monumental stair installation.

Sheathing installation at the east elevation.

Exterior studs and sheathing installation at the east elevation.

Precast installation at the east elevation.

Construction of the east exterior stair.

Electrical panels at the 1st floor electrical room.

Overhead rough-in and electrical room construction at the 2nd floor.

Overhead rough-ins at the 2nd floor.

Duct installation at the 3rd floor.

Roof drain piping.

Roof deck fireproofing.
Return to Construction Updates Index Page.