Uniform General Contract Conditions


APPENDIX F

VALPARAISO UNIVERSITY
UNIFORM GENERAL CONTRACT CONDITIONS
March 22, 2003


GENERAL AGREEMENT

    The provisions listed below are to be used by Vendor as the rules
    and guidelines governing Vendor work on the premises of Valparaiso
    University.

1.  OWNER'S REPRESENTATIVE

    1.1  Owner's Representative (O.R.) shall be the individual
         designated in writing by Owner.

    1.2  Duties of Owner's Representative

         1.2.1  The O.R. is authorized to act on behalf of Owner.  The
                O.R.  will provide general administration of the
                contract and shall fulfill the duties, rights and
                obligations of Owner under the Contract documents.

         1.2.2  All of Owner's instructions to Vendor shall be issued
                through the O.R.

         1.2.3  The O.R. will have authority to reject work which does
                not conform to the Contract Documents.

         1.2.4  The O.R. will prepare and initiate Contract Change
                Orders.  Changes will be funded only if valid Change
                Orders have been issued.


2.  FUNDAMENTAL PROVISIONS

    2.1  Vendor is to serve as General Contractor.


    2.2  Subcontracting: Subcontracting is permitted under the following
         conditions:

         2.2.1  Prior Approval: This contract and any part thereof shall
                not be subcontracted or assigned to another vendor
                without prior written approval of Owner.  Permission to
                subcontract or assign shall not unreasonably withheld.
                Subcontractor shall be responsible to Vendor, and shall
                receive all payments due for materials and labor from
                Vendor.  Vendor shall retain responsiblity for the Work.

         2.2.2  List of Subcontractors: Vendor shall furnish in writing
                to Owner within forty-eight (48) hours after the award
                of the contract, a list of the names of Subcontractors
                who will work on the project.
Valparaiso University        Telephone RFP  3/27/2003          Page  F-2


         2.2.3  Acceptable Subcontractors: Vendor is specifically
                advised that any person, firm or other party to whom it
                is proposed to award a subcontract under this RFP must
                (1) be registered in the state of Indiana and have an
                Indiana Contractor's registration number, and (2) be
                acceptable to Owner.  Owner's approval shall not be
                unreasonably withheld.


    2.3  Insurance: Vendor and each Subcontractor shall take out and
         maintain throughout construction period, insurance on an
         occurrence basis, naming "The Lutheran University Association,
         Inc., d/b/a Valparaiso University" as an additional insured,
         with minimum requirements as specified in the Subsections of
         this Section.  Vendor and Subcontractors, through Vendor, shall
         furnish to Owner five (5) copies of each Certificate of
         Insurance.

         2.3.1  Workmen's compensation and occupational disease
                insurance covering all employees in statutory limits who
                perform any obligations assumed under the Contract.

         2.3.2  Comprehensive General Liability Insurance and Automobile
                Liability Insurance in an amount not less than One
                Million Dollars ($1,000,000.00) for injuries, including
                accidental death, to any one person and subject to the
                same limit for each person, and in an amount not less
                than Two Million Dollars ($2,000,000.00) on account of
                any one occurrence.

         2.3.3  Property Damage Liability Insurance in an amount not
                less than One Million Dollars ($1,000,000.00).

         2.3.4  Medical Expense Insurance in an amount not less than One
                Hundred Thousand Dollars ($100,000) to any one person
                and subject to the same limit for each person.


    2.4  Code of Fair Practices: During the performance of this
         contract, Vendor agrees that Vendor will not discriminate
         against any employee or applicant for employment because of
         race, creed, color, religion, national origin, sex, age or
         physical or mental disability, or status as a Vietnam-
         era/disabled veteran; will so state in all solicitations or
         advertisements for employees placed by or on behalf of Vendor;
         and will advise labor unions, worker representatives, and
         employees of this contractual commitment.


    2.5  Successors and Assigns:  Owner and Vendor respectively bind
         themselves, their partners, successors, assigns and legal
         representatives to the other party hereto and to partners,
         successors, assigns and legal representatives of such other
         party in respect to covenants, agreements and obligations
         contained in the Contract Documents.  Neither party to the

Valparaiso University        Telephone RFP  3/27/2003          Page  F-3

         Contract shall assign the Contract in whole or in part without
         written consent of the other nor shall Vendor assign any moneys
         due or to become due to it hereunder, without the written
         consent of the Owner.  If either party attempts to make such an
         assignment without such consent, that party shall nevertheless
         remain legally responsible for all obligations under the
         Contract.


3.  SAFETY AND SECURITY PRECAUTIONS AND PROGRAMS


    3.1  Vendor shall be responsible for initiating, maintaining and
         supervising safety and security precautions and programs in
         connection with the performance of the Contract, including, but
         not limited to, safety and security of

         3.1.1  Employees of Vendor, Subcontractors, and other personnel
                related to the project;

         3.1.2  Owner's students, employees, guests, and visitors;

         3.1.3  Other individuals affected by the Work;

         3.1.4  The Work site and materials and equipment related
                thereto;

         3.1.5  Other property at or adjacent to the site, including
                landscaping, pavement, structures, and utilities


    3.2  Vendor is responsible for naming, in writing to Owner, a person
         on Vendor's staff who is responsible for safety and security,
         who will be available at all times that work by Vendor and/or
         Subcontractors is in progress.  This will normally be the
         Project Superintendent.


    3.3  Vendor shall be cognizant of and comply with applicable laws,
         ordinances, rules, regulations, and lawful orders of public
         authorities bearing on health and safety of persons or property
         or their protection from damage, injury or loss, including, but
         not limited to:

         3.3.1  Williams-Steger Occupational Safety and Health Act of
                1970 (OSHA)


    3.4  Vendor shall be responsible for exercising due care and good
         judgment in matters bearing on health and safety of persons or
         property or their protection from damage, injury or loss,
         including, but not limited to:

         3.4.1  Limiting equipment and structure loads to safe levels;


Valparaiso University        Telephone RFP  3/27/2003          Page  F-4


    3.4  Vendor shall erect and maintain, as required by existing
         conditions and performance of the Contract, reasonable
         safeguards for safety and protection, including posting danger
         signs and other warnings against hazards, promulgating safety
         regulations and notifying owners and users of adjacent sites
         and utilities.


    3.5  Vendor is solely responsible for responding to all safety
         inspections related to the Work, be they external, IOSHA, OSHA,
         EPA, or Owner; and be they with or without advance notice.
         Owner specifically reserves the right to conduct, or cause to
         be conducted, a safety inspection at any time.


    3.6  Hazardous Materials

         3.6.1   Owner shall provide to Vendor a list of known hazardous
                 chemicals within the project site to which their
                 employees may be exposed and suggestions for
                 appropriate protective measures.

         3.6.2   Vendor shall provide to Owner a list of known hazardous
                 chemicals that they anticipate will be used on site as
                 well as other pertinent information relating to
                 employee protection.  Vendor's Material Safety Data
                 Sheets (MSDS) shall be available to Owner upon request.

         3.6.3   When use or storage of explosives or other hazardous
                 materials or equipment or unusual methods are necessary
                 for execution of the Work, Vendor shall exercise utmost
                 care and carry on such activities under supervision of
                 properly qualified personnel.

         3.6.4   In the event Vendor encounters on the site material
                 reasonably believed to be asbestos or polychlorinated
                 biphenyl (PCB) which has not been rendered harmless,
                 Vendor shall immediately stop Work in the area affected
                 and report the condition to Owner in writing.  The Work
                 in the affected area shall be resumed only when Owner
                 has provided reasonable proof of the absence of
                 asbestos or polychlorinated biphenyl (PCB), or when
                 Owner has caused it to be rendered harmless.


    3.7  Vendor specifically agrees to hold Owner harmless for
         negligence shown to be the result of acts or failures to act by
         Vendor or Subcontractors.


    3.8  Emergencies: In an emergency affecting safety of persons or
         property, the Vendor shall act, at Vendor's discretion, to
         prevent threatened damage, injury or loss.

Valparaiso University        Telephone RFP  3/27/2003          Page  F-5


4.  RULES OF CONDUCT


    4.1  Vendor, Subcontractors, and others associated with the project
         are responsible for maintaining decorum.  This includes but is
         not limited to:

         4.1.1  Recognition that Owner has a religious affiliation.

         4.1.2  Recognition that Owner is multi-cultural.

         4.1.3  Recognition that this is a non-alcoholic campus.


    4.2  There are to be no incidents of offensive behavior within the
         site, in view of the site, or on or near the campus grounds at
         any location.  Offensive behavior includes, but is not limited
         to, harassment of any kind, use of inappropriate language, and
         engaging in any activity that is illegal or not consonant with
         Owner's principles.


    4.3  Driving and Parking on Campus

         4.3.1  Speed Limit:  This is generally 20 mph, but pedestrian
                traffic and/or road conditions may dictate a slower
                speed.  This applies to Vendors, Subcontractors and all
                related vehicles.

         4.3.2  Crosswalks:  Crosswalks in the center of campus are
                marked with white hash marks.  All traffic is to stop at
                these crosswalks to let pedestrians pass; this applies
                to Vendors, Subcontractors, and all related vehicles.

         4.3.3  Parking: It is the intent of the following university
                parking policy to keep the construction area as
                inconspicuous as possible and the campus attractive and
                pleasant for the public and students.  Vendor's
                understanding of this policy and cooperation in carrying
                it out is vital to the successful promotion and
                preservation of the University.

                4.3.3.1  All Vendor and Subcontractor vehicles and any
                         related vehicles are to park in designated
                         parking areas only.

                4.3.3.2  Vendors may be provided a company 1 (one) day
                         parking pass from the Valparaiso University
                         Police Department or a long term construction
                         pass from the Physical Plant Services located
                         at 1500 E. Lincolnway.  University construction
                         parking permits shall be displayed on all
                         company vehicles and trucks and private
                         employees' vehicles when parked on campus.

Valparaiso University        Telephone RFP  3/27/2003          Page  F-6


                4.3.3.3  Employee transportation from designated parking
                         to the job site shall be Vendor's
                         responsibility.

                4.3.3.4  Permits shall be removed from all trucks and
                         vehicles and returned to the issuing office
                         when the project is complete.

                4.3.3.5  Under no circumstances may Vendor and
                         Subcontractor vehicles, or any related
                         vehicles, park in spaces marked for Fire Lanes
                         (red), in No Parking Zones (yellow), in ADA
                         Spaces (blue), along streets or roads, on lawn,
                         on walks, or in any other than the designated
                         locations.  Parking tickets will be issued to
                         violators and/or trucks and vehicles will be
                         towed from campus at the registered owner's
                         expense.  Unpaid parking and/or towing fines,
                         including those of Vendor employees and
                         Subcontractors, will be withheld from Vendor's
                         payment.


    4.4  Water, Heat, Ventilation, Utilities and Other Facilities

         4.4.1   Restroom/toilet facilities in Owner's buildings may be
                 used only by prior approval.  In most cases, Vendor
                 will need to provide restroom/toilet facilities.

         4.4.2   Water in reasonable quantities may be obtained from the
                 nearest available outlets at no cost to Vendor in lieu
                 of Section 4.4.1 of the General Conditions.

         4.4.3   Electricity (120 volt) may be obtained from existing
                 outlets or panel at no cost to Vendor in lieu of
                 Section 4.4.1 of the General Conditions.


    4.5  Shipping and Receiving: Vendor shall not ship materials to
         Owner's Central Receiving Department or other departments.
         Vendor may ship to the Project Field Office, if any, and must
         be prepared to receive and unload materials.  Owner will not
         accept and/or unload and/or store Vendor materials.


    4.6  Cleanliness:

         4.6.1  Vendor shall at all times keep the site of the Work and
                adjacent premises as free from materials, debris,
                rubbish and trash as practicable, and shall remove same
                from any portion of the site if, in the opinion of
                Owner, such materials, debris, rubbish or trash
                constitute a nuisance or are objectionable in any way to
                the public.  Vendor shall be responsible for the removal

Valparaiso University        Telephone RFP  3/27/2003          Page  F-7


                of dirt accumulations or any other debris on campus
                roads and public streets and highways resulting from
                Vendor's operations of the Work.

         4.6.2  At the completion of the Work, Vendor shall remove all
                materials, implements, barricades, equipment, staging,
                piling falsework, debris and rubbish connected with or
                caused by operations for such Work immediately upon the
                completion of that Work and shall leave the premises in
                perfect condition insofar as affected by the Work under
                the Contract.  Fires for disposal of rubbish on the site
                are prohibited.

         4.6.3  If Vendor should fail to clean up the premises as
                required above, Owner, after giving Vendor forty-eight
                hours notice, may do so and charge the cost thereof to
                Vendor.


    4.7  Building Keys

         4.7.1  Vendor will be issued keys by Owner's Physical Plant
                Services Department (PPS) to gain access to buildings
                and/or to areas of the buildings.

        4.7.2  Vendor shall return the keys upon completion of the
                punch list, but not later than seven (7) days after the
                date of the punch list, to PPS

         4.7.3  PPS will issue a key receipt for the return of the keys
                in order that final payment for the project can be
                authorized.

         4.7.4  Vendor shall be responsible for the keys and rekeying or
                changing of locks, should the keys be lost by Vendor.

         4.7.5  Rekeying or changing of locks when commenced will not be
                stopped in the process should Vendor find the keys after
                notifying Owner that the keys are lost.


5.  WORK PLANNING AND REPORTING

    5.1  Vendor's Construction Schedules

         5.1.1  Vendor promptly after being awarded the Contract, shall
                prepare and submit for Owner's approval, a Vendor's
                construction schedule for the Work.  The schedule shall
                not exceed time limits current under the Contract
                Documents, shall be revised at appropriate intervals as
                required by the conditions of the Work and the Project,
                shall be related to the entire Project to the extent
                required by the Contract Documents, and shall provide
                for expeditious and practicable execution of the Work.

Valparaiso University        Telephone RFP  3/27/2003          Page  F-8


         5.1.2  Owner reserves the right to provide a list of critical
                dates when work at the site and/or interruptions
                should be avoided.

         5.1.3  Schedule shall include dates of planned service
                interruptions.  Revisions to the schedule of planned
                service interruptions shall not be made less than
                five days prior to such interruptions.

         5.1.4  Vendor shall prepare and keep current, for Owner's
                approval, a schedule of submittals which is coordinated
                with Vendor's construction schedule and allows Owner
                reasonable time to review submittals.

         5.1.5  Vendor shall conform to the most recent schedules.
                Vendor shall employ and supply a sufficient force of
                workmen, material, plant and equipment and pay when due,
                any workmen, Subcontractor or supplier for supplies
                furnished and otherwise prosecute the work with
                diligence to maintain the rate of progress indicated on
                the progress schedule, prevent work stoppage, and ensure
                completion of the project within the time specified.
                Should Vendor fail in any respect, Owner may require
                that additional workers, plant, and equipment be
                employed and placed on the work or require that hours in
                addition to regular hours be worked until progress is as
                scheduled, in any event with no additional cost to
                Owner.


    5.2  Meetings

         5.2.1  Owner Representative shall arrange and conduct a
                preconstruction meeting to review the Contract and other
                conditions of mutual interest, coordinate commencement
                of construction and discuss project procedures and
                Vendor's construction schedule, key personnel and
                Subcontractors.  An agenda will be made available.

         5.2.2  Vendor shall arrange and conduct progress meetings
                during construction.  Frequency of said meetings shall
                be determined at the preconstruction meeting at a
                mutually agreed time and location.  Time between
                meetings shall not be greater than two weeks.

         5.2.3  Vendor, Subcontractors, and Owner's Representative shall
                attend all meetings.

         5.2.4  Vendor shall prepare and provide minutes of the
                preconstruction and progress meetings to Vendor,
                Subcontractors and Owner within 2 days following each
                meeting.

Valparaiso University        Telephone RFP  3/27/2003          Page  F-9


    5.3  Supervision

         5.3.1  A list of Vendor's on-site key personnel with phone
                numbers and qualifications shall be submitted seven (7)
                days prior to the preconstruction meeting, along with
                Vendor's initial construction schedule.


    5.4  Access to Work

         5.4.1  Vendor shall provide Owner and Architect access to the
                Work in preparation and progress wherever located.

         5.4.2  Vendor shall furnish Owner all necessary assistance to
                facilitate inspections throughout the process of
                manufacture or construction, or for the examination of
                any materials entering into the Work or for any other
                purpose required in the discharge of Vendor's duties.


    5.5  Recordkeeping and Record Retention

         Vendor shall establish and maintain adequate records of all
         expenditures incurred under the contract.  All records shall be
         kept in accordance with generally accepted accounting
         procedures.  All procedures shall be in accordance with
         Federal, State and local ordinances.

         Owner shall have the right to audit, review, examine, copy, and
         transcribe any pertinent records or documents relating to any
         contract resulting from this RFP held, owned, or controlled by
         Vendor.  Vendor shall retain all documents applicable to the
         contract for a period of not less than three (3) years after
         final payment is made.


6.  VENDOR RESPONSIBILITIES

    6.1  Site conditions: Vendor is responsible for informing himself of
         all the site conditions.  There shall be no Change Notices for
         unrevealed situations.

    6.2  Permits: Vendor is responsible for acquiring all State and
         Local Permits and approvals and their display and maintenance.
         Fees for those are to be included in the project.

    6.3  Codes and Standards: All work shall be performed per the
         following codes and standards as applicable to the task(s)
         performed.  If Vendor performs Work knowing it to be contrary
         to laws, statutes, ordinances, building codes, and rules and
         regulations without such notice to Owner, Vendor shall assume
         full responsibility for such Work and shall bear the

Valparaiso University        Telephone RFP  3/27/2003         Page  F-10


         attributable costs.  The latest editions of these Codes and
         Standards shall be applicable unless otherwise designated.
         Where conflicts exist from one code to another, the more
         stringent requirement shall apply.

         6.3.1  Building Officials and Code Administrators (BOCA)
                International Inc. Basic Building Code, BOCA Basic
                Plumbing Code, BOCA Basic Mechanical Code

         6.3.2  State of Indiana State Building Code

         6.3.3  National Fire Protection Association (NFPA) 101 Life
                Safety Code

         6.3.4  National Electric Code (NEC)

         6.3.5  Williams-Steger Occupational Safety and Health Act of
                1970 (OSHA)

         6.3.6  American National Standards Institute (ANSI)

         6.3.7  Institute of Electrical and Electronics Engineers (IEEE)

         6.3.8  Electronics Industry Association (EIA) 568/569/606

         6.3.9  Indiana Electrical Code and/or National Electrical
                Code (NEC)

         6.3.10 National Board of Fire Underwriters (NBFU)

         6.3.11 Underwriter's Laboratories, Inc. (UL), Federal
                Specifications

         6.3.12 Rural Electric Association - Telephone Division
                Standards

         6.3.13 FCC Codes and Regulations

         6.3.14 Americans With Disabilities Act (ADA).


    6.4  Location of Utilities

         At least two (2) working days before excavating, Vendor shall
         arrange for all existing utilities to be located and marked.

         6.4.1  For those entities having utilities on campus (other
                than Owner), Vendor shall call 800-382-5544 and request
                existing utilities be located and marked in accordance
                with the Underground Plant Location Service System
                guidelines and regulations.

         6.4.2  Vendor shall contact Owner also and request Owner's
                existing utilities be located and marked.

Valparaiso University        Telephone RFP  3/27/2003         Page  F-11


    6.5  Taxes

         Vendor shall pay sales, consumer, use and similar taxes for the
         Work or portions thereof provided by Vendor which are legally
         enacted when proposals are received or negotiations concluded,
         whether or not yet effective or merely scheduled to go into
         effect.

         Upon completion of the contract, but before final payment,
         Vendor shall furnish Owner, in duplicate, a Owner's Statement
         properly executed and sworn to, list all Indiana sales and/or
         use taxes, and local option sales taxes where applicable, paid
         by Vendor and all Subcontractors on all supplies, and materials
         and on all equipment incorporated into and made part of the
         Work.  Blank copies of Owner's Statements will be furnished to
         Vendor by Owner upon request.


    6.6  Salvage Materials

         6.6.1  Salvage materials as listed in the Technical
                Specifications shall be delivered to Owner's on-campus
                storage.

         6.6.2  Remaining materials salvaged by Vendor shall become the
                property of Vendor and shall be promptly removed from
                the site.

         6.6.3  Salvage materials which become the property of Vendor
                shall not be sold upon Owner's property.  Such materials
                shall be removed from the site for disposition.


    6.7  Waste Materials: Vendor shall remove all waste materials from
         the project site.  Disposal shall be in accordance with law.


7.  PAYMENTS AND COMPLETION

    7.1   CONTRACT SUM

          The Contract Sum is stated in this Agreement and, subject to
          authorized adjustments, is the total amount payable by the
          Owner to Vendor for performance of the Work


    7.2   SCHEDULE OF VALUES

          Before the first payment, Vendor shall submit to Owner a
          schedule of values allocated to various portions of the Work.
          This schedule, when approved by Owner, shall be used as a
          basis for Vendor's Applications for Payment.

Valparaiso University        Telephone RFP  3/27/2003         Page  F-12


    7.3   APPLICATIONS FOR PAYMENT

          Not more than once a month and as appropriate to the progress
          of the Work, Vendor shall submit to Owner an itemized
          Application for Payment, prepared on a form furnished by
          Owner, subject to the following

          7.3.1  Unless otherwise provided in the Contract Documents,
                 payments shall be made on account of materials and
                 equipment delivered, subject to Owner approval.

          7.3.2  Vendor warrants that clear title to all Work covered by
                 an Application for Payment will pass to Owner no later
                 than the time of payment.

          7.3.3  Owner shall review Application for Payment with
                 reasonable promptness and, if approved, released
                 payment to Vendor.  Applications which are not approved
                 shall be returned to Vendor, accompanied by a written
                 statement giving the reason(s) for such return.

          7.3.4  Owner will withhold until final payment, retainage in
                 an amount consistent with applicable law.


    7.4   DECISIONS TO WITHHOLD PAYMENT

          7.4.1  Owner may decline to approve an Application for Payment
                 and may withhold or rescind payment in whole or in
                 part, to the extent necessary to reasonably protect
                 Owner, due to

                 7.4.1.1  defective Work not remedied;
                 7.4.1.2  third party Claims filed pursuant to
                          applicable law;
                 7.4.1.3  failure of Vendor to make payments properly to
                          Subcontractors for labor, materials or
                          equipment;
                 7.4.1.4  reasonable evidence that the Work cannot be
                          completed for the unpaid balance of the
                          Contract Sum;
                 7.4.1.5  damage to Owner or another Vendor;
                 7.4.1.6  reasonable evidence that the Work will not be
                          completed within the Contract Time, and that
                          the unpaid balance would not be adequate to
                          cover actual or liquidated damages for the
                          anticipated delay; or
                 7.4.1.7  persistent failure to carry out the Work in
                          accordance with the Contract Documents.

          7.4.2  When the above grounds are removed, payment shall be
                 made for amounts withheld because of them.

Valparaiso University        Telephone RFP  3/27/2003         Page  F-13


    7.5   PROGRESS PAYMENTS

          7.5.1  Owner shall make payment in the manner and within the
                 time provided in the Contract Documents.

          7.5.2  Vendor shall promptly pay each Subcontractor and
                 material supplier, upon receipt of payment from Owner,
                 the amount to which said Subcontractor is entitled.

          7.5.3  Owner shall not have an obligation to pay or to see to
                 the payment of money to a Subcontractor except as may
                 otherwise be required by law.

          7.5.4  The payment schedule will be periodic based upon
                 delivered goods.  Payments will be capped with retained
                 percentage until successful completion of acceptance
                 testing.  The suggested exceptions are noted as
                 follows:

                 10%    Upon receipt of design drawings and detailed
                        specifications.

                 50%    On a periodic basis based upon the delivery of
                        materials on site and installation services.

                 90%    Upon Substantial Completion

                 95%    Upon successful completion of acceptance test.

                 100%   Final Acceptance and return of all keys and
                        other Owner property.

          7.5.5  Under no circumstances shall the proposed payment
                 schedule require payment of more than ninety-five
                 percent (95%) of the total system acquisition price
                 prior to system acceptance.


     7.6  SUBSTANTIAL COMPLETION

          Substantial Completion is the stage in the progress of the
          Work when the Work or designated portion thereof is
          sufficiently complete in accordance with the Contract
          Documents so Owner can occupy or utilize the Work for its
          intended use.

          7.6.1  When Vendor considers that the Work, or a portion
                 thereof which Owner agrees to accept separately, is
                 substantially complete, Owner shall prepare and submit
                 to Vendor a comprehensive list of items to be completed
                 or corrected.  Vendor shall proceed promptly to
                 complete and correct items on the list.  Failure to
                 include an item on such list does not alter the
                 responsibility of Vendor to complete all Work in
                 accordance with the Contract Documents.  When Owner

Valparaiso University        Telephone RFP  3/27/2003         Page  F-14


                 agrees the Work or designated portion thereof is
                 substantially complete, Vendor will prepare a
                 Certificate of Substantial Completion which shall
                 establish the date of Substantial Completion, shall
                 establish responsibilities of Owner and Vendor for
                 security, maintenance, heat, utilities, damage to the
                 Work and insurance, and shall fix the time within which
                 Vendor shall finish all items on the list accompanying
                 the Certificate.  Warranties required by the Contract
                 Documents shall commence on the date of Substantial
                 Completion of the Work or designated portion thereof
                 unless otherwise provided in the Certificate of
                 Substantial Completion.  The Certificate of Substantial
                 Completion shall be submitted to Owner and Vendor for
                 their written acceptance of responsibilities assigned
                 to them in such Certificate.


     7.7  PARTIAL OCCUPANCY OR USE

          7.7.1  Owner may occupy or use any completed or partially
                 completed portion of the Work at any stage when such
                 portion is designated by separate agreement with
                 Vendor, provided Owner and Vendor have accepted in
                 writing the responsibilities assigned to each of them
                 for payments, retainage if any, security, maintenance,
                 heat, utilities, damage to the Work and insurance, and
                 have agreed in writing concerning the period for
                 correction of the Work and commencement of warranties
                 required by the Contract Documents.

          7.7.2  Immediately prior to such partial occupancy or use,
                 Owner and Vendor shall jointly inspect the area to be
                 occupied or portion of the Work to be used in order to
                 determine and record the condition of the Work.

          7.7.3  Unless otherwise agreed upon, partial occupancy or use
                 of a portion or portions of the Work shall not
                 constitute acceptance of Work not complying with the
                 requirements of the Contract Documents.


     7.8  ACCEPTANCE AND FINAL PAYMENT

          7.8.1  Upon receipt of written notice that the Work is ready
                 for final inspection and upon receipt of a final
                 Application for Payment, Owner will promptly make such
                 inspection and, when the Work is found acceptable under
                 the Contract Documents and the Contract fully
                 performed, Owner will promptly issue a Notice of
                 Acceptance.


Valparaiso University        Telephone RFP  3/27/2003         Page  F-15


          7.8.2  If, after thirty days from the date of the Notice of
                 Acceptance, Claims are on file with Owner, Owner shall
                 withhold a sum equal to double the total amount of
                 claims on file or 5% of the contract price, whichever
                 is less, until such Claims are released or otherwise
                 adjudicated.

          7.8.3  Final payment shall not be made until Vendor has
                 complied in full with all requirements of these General
                 Conditions.

          7.8.5  The making of final payment shall constitute a waiver
                 of all Claims by Owner except those arising from:

                 7.8.5.1  unsettled Claims,

                 7.8.5.2  faulty or defective Work, appearing after
                          acceptance,

                 7.8.5.3  failure of the Work to comply with the
                          requirements of the Contract Documents, or

                 7.8.5.4  terms of any special guarantees and warranties
                          required by the Contract Documents.

          7.8.6  The acceptance by Vendor of final payment less
                 retainage shall constitute a waiver of all Claims
                 except those previously made in writing and still
                 unsettled.