| |
| |
| Chapter Projects : The
Student Bridge : Recent News |
| |
 |
 |
-
Tuesday, April 22nd -
Progress!
-
After a last minute push
to complete the form work
for the legs, we now have
the concrete placed for all
4 columns. The 40 ton
crane arrived at 7 am, and
the cement truck and truck
delivering the cement bucket
both arrived right at 8 am.
And by 9 am, it was all
over, a mere 6 hours after
the form work had been
finished with the aid of
work lights.
-
Saturday, April 16th
- Shredded
-
Wednesday, April 6th -
Work has restarted for the
Spring!
-
After waiting out what
was hopefully the last bit
of cold weather for the
year, work has begun on the
campus site. The
retaining wall itself has
been filled with drainage
rock, and the brush is being
cleared from both sides of
the bridge, so that it can
been seen more clearly from
both the library and US 30.
The majority of the cap
stones for the wall are also
going to be cut and epoxied
into placed this week.
Someone should be out at the
bridge most any day after
4.30 pm on weekdays, and
most of the day on
Saturdays. Work is
also beginning on the
Vineyard site this weekend
with the preparations of the
existing footers for use
with the new supports we
will be pouring for the
bridge. Finally, we
are always looking for more
help, so if you want to get
involved with the project,
its never too late.
Please contact
Derek Snyder so you can
get up to speed with the
workdays coming up.
-
Monday, March 28th - DNR
-
After much help from DLZ,
and not much help from the
Department of Natural
Resources, we have finally
have (hopefully) the last outstanding
permit approved for placing
the replacement bridge over
Salt Creek. Expect to
see a flurry of work in the
coming weeks. And with
the weather starting to
slowly edge towards what
might be considered warm, we
will finally be scrub out
the undergrowth on the
campus site in the very near
future, as well as a whole
host of other finish work
(backfilling the exterior of
the wall, cap stones on the
wall, the list goes on and
on). Watch this space,
as things should start to
happen in the final push for
completion.
-
Wednesday, February 9th -
No News is Not Bad News
-
As we're currently in
the middle of the winter, it
shouldn't be that big of a
surprise that work has
slowed down, but take care
to note it hasn't stopped
completely. Much
planning is being done and
many materials are being
sourced in anticipation of
the weather warming up
enough for work to begin
anew in the coming weeks.
-
Wednesday, December 15th
- Backfilled
-
In a final push in the
middle of finals week, the
west ramp was backfilled
with sand. With three
full dump truck loads of
sand from GE Marshall, Prof.
Mack at the helm of a
Bobcat, and a number of
students with shovels,
including our two newly
graduated students, Brett
Iafigliola and Kristine
Martin, the ramp was
backfilled and compacted by
days end.
-
Tuesday, December 7th -
Website News
-
In a bit of uniquely web
related news, we are working
on revamping the photo
gallery, as it has now
ballooned to over 1000
pictures. The existing
full gallery will remain, but
a new gallery will added
which will be more concise in the images
of the project it presents.
Once finished, over the
course of the next few
weeks, the new gallery should
be much easier to pursue.
-
Saturday, November 20th -
Retaining Wall Finished
-
Early Saturday morning, the
last stone was laid on the
west wall, completing the
month long work on the two
walls. But as ever,
there is still lots to be
done. The walls have
been set, but they still
need to be backfilled,
capped, light, and
landscaped.
-
Monday, October 18th -
Retaining Wall Work
-
Work continues on the
east retaining wall.
For the foreseeable future,
we plan to be out at the
bridge site every day
starting at 4 pm.
To quote Brett Iafigliola,
our de facto project manager,
"If you're free earlier,
chances are good that
someone is out there then
too. And, if for some
outlandish reason that there
is no work that day, the
worst that can happen is
that you'd wander all the
way out there, only to gaze
upon the bridge and turn
back."
 |
 |
-
Friday, September 24th
-
The bridge has returned
to campus after 37 years of
absence! The bridge
was placed on its new
footings, and brings to a
close one segment of the
project. But much much more
remains to be done!
The bridge needs to be
redecked with lumber, the
approaches to the bridge
need to be built, lit, and
landscaped, and this is not
even getting to the
replacement bridge for
Vineyard. Please
contact
Brett Iafigliola
if you are interested in
getting involved with the
project, as there is lots
left to do!
-
Thursday, September 23rd
-
The restoration
process continues. The
project is now another step
closer to being
finished. GE Marshall
picked up the bridge from
Preferred Contractors today,
and the bridge should be
ready to be placed in its
new home in the coming
weeks. We would
again like to thank GE
Marshall for all of their
help with this project.
-
Tuesday, September 14th
-
The bridge has been
sandblasted and is starting
to be repaired at Preferred
Contractors in Michigan
City. The repairs have
been approved, and the
bridge should be ready to
journey to its new home on
campus by next week.
-
Tuesday, September
7th
-
Starting at 5:30
am, the Student Bridge was
prepped for removal,
removing a bit of cross
bracing on the under
side of the bridge in order
to fit the two lifting
members. The bridge
was then rigged up, a
spreader bar was fit to a
crane rented from Calumet
Crane Company and then attached to
the bridge rigging and
pulled into tension.
The bridge was then cut free
of its legs and loaded onto
the back of a lowboy
trailer provided by GE
Marshall Excavating. Both sets of
legs were then cut free of
their foundations and loaded
onto the trailer as well.
The bridge is now on its way
to be sandblasted, repaired,
and repainted at Preferred
Contractors in Michigan
City. We would also
like to extend our thanks to Schirmer Construction for
their onsite expertise lent
to the work.
Back To The Student Bridge
Project Home Page |
| |
|
|
|
|
|
|